Albany High construction nears completion; board hears list of punch‑list items and warranty fixes

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Turner Construction and district staff reported Phase 4 occupancy with ongoing punch‑list work, long‑lead theatrical equipment arriving in autumn, and several deficiencies including window‑edge leaks and subbase issues on the loop road that require remediation.

Turner Construction reported that Phase 4 of the Albany High School project is occupied for the start of the school year and that contractors are finishing interior punch‑list items. At a board presentation, Turner’s Bob Grande and district staff summarized completed elements and identified remaining deficiencies that must be corrected before final closeout.

The board heard that theatrical lighting and rigging approved as additional scope are long‑lead items projected to arrive in October or November; Turner projected installation and completion around Thanksgiving. Nursing and other added spaces are in use with minor remaining punch items.

Construction staff described water infiltration traced to specific…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans