Tanner's Run work moving in phases; easements signed, Army Corps review pending

5737919 · September 9, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

County and municipal officials reported Sept. 8 that the first phase of repairs to Tanner's Run — including work to a collapsed pipe near an apartment complex — is planned once the Army Corps of Engineers approves the project and a contractor commits to a date.

Officials reported Sept. 8 that a multi-jurisdictional effort on Tanner's Run is advancing in phases; staff and local officials described immediate work to stabilize a collapsed pipe near an apartment complex as the first priority.

Bob Spangler, who attended local meetings, said the initial focus is clearing and stabilizing the area around the pipe outlet near the apartment complex, where erosion has undermined a parking area. County staff read an email update from Chris Dietz stating that easements for the collapse-opening piece are signed and that the county is waiting on U.S. Army Corps of Engineers approval and on a contractor’s commitment to a schedule.

“The last contractor contact...said he could have the work done before September,” Dietz’s email said, according to staff. County staff noted the borough has withheld some bond funds pending verification that the detention facility is operating as intended; engineers were conducting on-site infiltration testing to confirm performance.

Why it matters: The project affects a residential area where erosion has damaged property and where the potential for sewer impacts and public-safety hazards was raised. Staff said short-term stabilization is the immediate priority while longer watershed-level work is planned.

Ending: Staff said they will report results of the Army Corps review and the contractor’s schedule once the county receives them and that the next steps will depend on the initial stabilization work and the borough’s bond-release conditions.