Parks staff outline restroom design, trail reconstruction and signage plans; Rainbow Memorial Park work delayed
Summary
Parks staff reported progress on design work for a REITs ballfield restroom/concession building, ongoing trail and court reconstructions, Lakeshore Park signage and a delayed intersection project that pushes Rainbow Memorial Park improvements beyond the current capital plan window.
Parks Department staff updated the Parks Advisory Board on several ongoing and planned projects, including design work for a restroom/concession building at the REITs ballfields, road and trail reconstruction work, signage for Lakeshore Park and a delay to Rainbow Memorial Park improvements tied to a Wisconsin Department of Transportation (DOT) project.
Ray Mauer (staff member) told the board the city has contracted TR Carroll to design a new restroom/concession building at the REITs complex; staff are collecting background information and will follow up on scheduling. The department has budgeted funds in the capital improvement plan (CIP) for phased work on the REITs complex,…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat