Staff outlines $15 million in active grants; council hears proposed reallocations and project timing

5731935 · September 9, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City staff briefed the council on 13 active grants totaling about $15 million, including major State Water Board funds for water-distribution improvements and several transportation and community-development grants.

City staff presented an overview of 13 active grants totaling about $15 million, summarizing funding sources, current project status and near-term tasks.

Melissa, the city’s grant manager, said the largest awards are from the State Water Board for water-distribution system improvements and related design work. She outlined near-term activity on road and pedestrian-safety projects (Mount Shasta Boulevard partial completion, Lake Street planning with a STIP grant, and ongoing Safe Streets work), senior snow-removal services out to bid, and an ongoing parks and recreation grant under which staff anticipate funds will be reallocated to better meet community needs.

Staff also discussed a grant with multiple subprojects that includes visitor-center work, City Hall plaza landscaping, and an originally budgeted paving project for a Chestnut Street lot. Staff described informal, state-level approval to shift some allocations from paving to other priorities such as a parking plan and roof repairs at the visitor center; staff said they would prepare any required reallocation paperwork and budget adjustments.

Council members asked for further discussion about specific allocations and agreed to review Prop 68 (labeling in transcript: the "prop 60 8" reference) funds at the finance committee. Staff said three projects are expected to complete in the 2025–26 fiscal year, and that the water-distribution construction may begin imminently. The Landing master-plan grant will run through 2027, giving time to complete master planning and outreach.

Staff noted grants require substantial staff time and cross-department coordination; the presentation was informational and council did not take a separate vote on the grant portfolio during the meeting. Council members requested further review of the visitor-center and Chestnut-parking reallocations at upcoming finance-committee meetings.