Capital projects dashboard: McEwen, Robinson Lake and Southeast Park show progress; Columbia right-of-way work ongoing
Summary
City staff updated the council on capital projects: McEwen work progressing with blasting planned, Robinson Lake and Southeast Park moving material, Columbia right-of-way acquisitions underway, and traffic and intersection concerns raised for Carruthers Parkway and Lewisburg/Donaldson Creek.
City staff provided the council with the August capital projects dashboard and highlighted progress on multiple projects, including McEwen, Robinson Lake, Southeast Park and right-of-way activity on the Columbia project.
Paul reported McEwen is progressing well and contractor Vulcan is preparing to blast within days after completing pre-blast surveys. He said Players Mill and Road Of The Round Table was closed for related work…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat