Princeton raises water capacity fee for new construction to $25, effective Sept. 9

5731326 · September 8, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Board of Commissioners voted 4-0 to increase the town's water capacity fee for new construction from $15.20 to $25 to align with county cost pressures and to cover a recently purchased 30,000-gallon allocation.

The Princeton Board of Commissioners voted 4-0 on Sept. 8 to raise the town's water capacity fee for new construction to $25 per unit (based on the 250 gallons-per-day calculation used in staff materials), effective the next day.

Town staff presented the adjustment as a response to a Johnston County bulk rate increase the county will implement Nov. 1 and to cover the town's recent purchase of extra capacity. The change will apply to new development and not to existing residents or transfers of existing service.

A staff member told the board that the current capacity charge is $15.20 per unit, which the town applies on a 250-gallons-per-day basis; at that basis the present per-lot charge is $3,800. Raising the fee to $25 per unit would increase the per-lot capacity charge to $6,250 (an increase of $2,450 per lot on the 250-gpd basis), staff said. The staff recommendation cited town purchases of 30,000 gallons of additional capacity for $405,000 as part of the fiscal response to county rate changes.

Explaining the recommendation, a town staff member said, "It is my recommendation that we charge $25," and noted that adopting that level now would likely reduce the need for a larger increase next year if county rates continue to climb. The staff presentation included a chart projecting further county increases in coming years and showed that a $25 rate would cover the town's projected costs for the near term.

Commissioners asked whether the change would be passed on to developers; staff said developers and builders have been notified and typically the fee increase is passed along. The board voted to adopt the $25 rate and directed staff to make the change effective immediately; the motion passed by a 4-0 vote.

Action details: motion to modify the town's water capacity fee to $25 per unit (250 gpd basis), effective Sept. 9; majority approved 4-0. The change affects only new construction and not existing accounts, per staff.