Planning commission grants conditional approval for Fourth and Booth distribution center revision at 436 Highland Ave

5730624 · September 8, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Commissioners voted Feb. 12 to approve the revised final plan for a 9,600 sq ft tractor-trailer and bus repair building at 436 Highland Avenue (an extension of 3000 West Fourth Street) subject to engineering, PennDOT, DelCora/Delaware County and fire-department conditions.

The Chester City Planning Commission on Feb. 12 conditionally approved an amended final land development plan for a small service garage at 436 Highland Avenue — part of the Fourth and Booth Distribution Center project. The applicant, Alliance 436 Highland Avenue, LLC (Alliance HP Management, LLC), proposed a one‑story, 9,600-square-foot building for tractor‑trailer and bus repair on previously approved impervious surface; the commission’s approval was conditioned on satisfying outstanding engineering, PennDOT and county conservation requirements.

City planning staff and the city engineer noted this submission revises a previously approved two‑phase development and does not increase overall impervious coverage (the applicant said the proposal reduces impervious area by approximately 500 square feet). The applicant said most site infrastructure — sidewalks, stormwater controls and prior roadway improvements tied to the earlier large warehouse approval — already exist and that the proposed small building replaces parking that had been allocated for trucks.

Reviewers asked the applicant to submit a revised stormwater report, closeout documentation for the initial PennDOT Highway Occupancy Permit associated with prior work, any necessary HOP or utility road-opening permits for new service connections, and a truck‑turning exhibit confirming fire‑apparatus access. The applicant said the existing stormwater BMP was previously accepted by DelCora and DEP as a field change and that they would submit updated calculations and provide minor‑amendment documentation to the Delaware County Conservation District as required.

The fire department reviewed truck access and confirmed that a standard 42‑foot ladder truck could be maneuvered through the site. The planning commission motion approved the revision subject to the applicant addressing the city engineer’s February 6 review letter, resolving MPDES/Delaware County Conservation District minor‑amendment paperwork, obtaining any required PennDOT approvals for utilities and resolving final items from the Shade Tree Commission and zoning/construction review. The motion passed on a voice vote.