Maple Glen roof work completed; committee approves $272,454 change orders after rotten plywood found

5725048 · September 6, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The finance committee approved two change orders totaling $272,454.40 after contractors discovered widespread deteriorated plywood under Maple Glen Elementary's roof; the cost was covered by unit pricing in the contract.

Upper Dublin School District staff told the finance committee on Aug. 20 that roof replacement work at Maple Glen Elementary is finished and that two change orders were required after crews discovered extensive plywood deterioration beneath the shingles.

Facilities staff said the plywood used in the original roof installation had warped and curled as it aged, a condition consistent with pressure-treated plywood the industry later abandoned; the district’s architect and roofer inspected exposed areas during removal and confirmed the…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans