Jonesboro council receives wide-ranging capital projects update; bond funds drive sidewalks, drainage, rail and park work
Summary
City staff briefed the Jonesboro City Council on a slate of bond- and grant-funded capital projects including road overlays, sidewalks, drainage work, rail-crossing upgrades, and park renovations; staff said several property acquisitions and a possible condemnation remain on the University Heights trail and South Caraway Road projects.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
City staff gave the Jonesboro City Council a detailed update Tuesday on ongoing capital projects, saying bond funds passed in July have accelerated work on road overlays, sidewalks, drainage and several park improvements.
The update, delivered by Craig, a city staff member, covered dozens of active projects and near-term milestones. "They're about a third through for the year," Craig said of the 2025 overlays, and he told council staff expect crews to continue work through the fall to meet the budget cycle. He noted the city is advancing both bond-funded and grant-funded projects in parallel.
Why it matters: the bond authorization the council approved in July is enabling projects that staff said would otherwise be delayed or paused. Several projects listed as 2026 construction or requiring outside approvals also depend on property agreements and state participation.
Staff highlighted street and traffic work: the city has completed five speed-table installations and created a policy that screens candidate streets by traffic volumes and posted speeds. Greg, a traffic staff member, summarized the screening criteria as a range of roughly 300 to 1,500 vehicles per day and posted speeds under 35 mph (with a 25 mph target for the calmer streets). Craig cautioned that on higher-volume or faster roads, speed tables can become a detriment rather than a safety feature.
Traffic and pedestrian projects named in the update include the North Church hawk signal (equipment ordered; staff hope for installation before year end), the Johnson Avenue side path and turn-lane project (bond-funded; eight properties touched, mostly temporary easements, now in acquisition), and a Southwest Drive/Culver House pedestrian improvement (plans near 90 percent complete). Craig said the Johnson Avenue project has obtained permits and that property agreements will be coming to council in the next couple of months.
Drainage and sidewalk work: staff reported completion of Meadowlark drainage improvements and Olive and Vine Street drainage work, with Maplewood Terrace drainage improvements and a Butler Ditch floodway restudy scheduled to start this fall. On sidewalks, the Madison sidewalk project is complete; the Jefferson Avenue trail (bond-funded) has advanced from Flint to Walnut since July.
Rail and safety projects: the city completed a switch-point protection project and has the MLK crossing project under contract, but staff are awaiting a notice to proceed from the state Department of Transportation contractor. Craig said the city has installed sensors for a "train info" system and is calibrating communications with the 911 system; foundations for digital message boards to warn motorists are in design.
Grant-funded work: completed items include a downtown-to-state project and the Melrose sidewalk. Staff said a Jet bus-stop project and an "Abilities Unlimited" stop are under contract but the bus stops themselves may not be available until December, which could delay on-the-ground construction. The rail-crossing-elimination grant remains under contract negotiation.
Land acquisition and condemnation risk: Craig said two remaining properties must be acquired for the University Heights trail; one belongs to Arkansas State University and the other owner has not cooperated, making condemnation likely. Similarly, two properties for the South Caraway Road project remain to be acquired; staff said they expect the project to go to construction in 2026 if utility adjustments (city water/wastewater) are resolved.
Parks and recreation: Danny, parks staff, told council that aging pavilions and playground equipment are being evaluated. He said one pavilion recently came down and insurance is covering replacement; another pavilion will be replaced after inspection. Danny described Rotary Playground as the city's most-used playground and said it is due for replacement: "You can usually expect a playground to at least be a 25 year playground," he said, adding that the Rotary equipment was installed in February 2005. He also said a playground was delivered for University Lions Park and installation should begin within two weeks; that site will be the city's fourth inclusive playground and the first on the north side of town.
Mayor Bridal also gave updates that touch on capital planning, including private-development interest in Turtle Creek Mall (the mayor said investors may bid on the property within about a week and a half) and the ongoing Justice Complex inspections. "Results of the Justice Complex inspections have yet to produce a definitive answer for timeline for solid resolution," Bridal said, adding the city is using community centers for continuity while officials evaluate next steps.
Public comment and safety concerns: in public comment, James Owen Hynes, 508 Ridgecrest, urged the council to plan for additional crossings over the railroad and safer conditions on older streets such as Culver House, saying some stretches lack sidewalks and shoulder space for pedestrians and cyclists. Hynes pressed the council to begin planning now for longer-term, expensive solutions such as an overpass on the west side of the Arkansas State campus.
Next steps and timing: staff repeatedly gave target windows rather than firm completion guarantees. Several projects listed design milestones in September–November 2025 and construction windows in 2026; the University Heights property acquisition and pending condemnations are the most immediate obstacles that could delay start dates.