Woodbury transportation update: Valley Creek, Interlochen, Central Park access and force‑main delay affecting Eastview Road
Summary
City transportation staff reported progress and timing on several projects including Valley Creek Road, Interlochen Parkway, Pioneer Drive, Central Park Place work, and a Met Council force‑main project that has delayed Eastview Road work to next year.
City transportation staff reported Sept. 24 that a series of water‑treatment, pipeline and roadway projects across Woodbury are nearing completion but that some segments remain under construction and one project has been delayed by a regional utility contractor.
Chris Hartsell, presenting the transportation report, said most 2025 construction is tied to a water‑treatment plant and associated pipeline work. Hartsell reported Interlochen Parkway and Pioneer Drive work (Valley Creek Road to Juniper Lane) are open to…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat