Queen Creek CIP update: new signals, roundabout, Barney Complex progress and LG construction
Summary
Dave Lipinski, the town’s CIP director, told the council two traffic signals are active, a roundabout and school access improvements are complete, and the Barney Complex and major waterline segments are progressing toward year‑end completion.
Dave Lipinski, the town’s capital improvement projects director, briefed the Queen Creek Town Council on the town’s quarterly CIP update, reporting several completed items and projects under construction.
Lipinski said the traffic signal at Riggs Road and Harvest Lake Drive was activated the morning of the report and that a second signal at Queen Creek and 2 Twentieth (near the former Barney Complex) is active with minor punch‑list work remaining. "This signal is now active," he said of Riggs and Harvest…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat