Cookeville approves change order for energy department site work, adds contingency for permit remobilization

5719513 · August 22, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved a W&O Construction change order and contingency funding for site work at the city’s new energy facility; staff said low bid was $1,936,875 and the full change order with contingency totals $2,371,132.35 if remobilization is needed.

The Cookeville City Council on Aug. 21 approved a change order for site work at the city’s new energy department facility and authorized an additional contingency for potential remobilization tied to permit timing.

Mister Haney told council W&O Construction received five bids and Clark Excavation was the low bidder at $1,936,875 for the site-work phase. Haney said the change order as presented, which includes contingency and bond amounts, totals $2,356,132.35; he said staff requested an additional $15,000 in case the contractor must remobilize if an ARAP permit’s timing requires it, producing a potential total of $2,371,132.35.

Councilman Gilbert moved to approve the change order; Vice Mayor Eldridge seconded. The council voted 5-0 to approve.

Haney said the work is being completed in three phases and that phase 1 (building pad) has a completion date of Nov. 10 as shown in the project materials. He recommended approval and said public works, energy and water-quality reviewers had examined the plans. The transcript does not record additional contract amendments beyond the contingency described, nor does it include any public objections.