Commission approves certificate of substantial completion for WPC administration building; final change orders raise total to about $889,466
Summary
The commission approved a certificate of substantial completion for the Water Pollution Control (WPC) administration building. Staff reported a guaranteed maximum construction price of $754,120.56 and change orders and other costs bringing total project cost to $889,466.38; two minor items remain to finish.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
The Leavenworth City Commission approved a certificate of substantial completion for the WPC (Water Pollution Control) administration building and set a ribbon-cutting date, city staff said.
City staff told commissioners the city identified a critical need to relocate the WPC administrative offices for health and safety reasons and contracted a design-build team in 2023. "Cost for construction of the new administration building was $754,120.56," a staff member said, adding that a guaranteed maximum price covered the construction. Staff said change orders related to unexpected site conditions and utility relocations and other adjustments added roughly $17,500 in change-order costs; total project cost including design, construction and three change orders was $889,466.38.
Staff noted two minor punch-list items remained on the certificate of substantial completion: delivery and installation of a laboratory sink/countertop and minor touch-up work at the facility. The commission approved the certificate and commissioners heard that the new building has already been occupied for operations for about two weeks. A ribbon cutting was scheduled for Friday the 19th at 2:30 p.m., staff said.
Vote and context: A motion to approve the certificate of substantial completion was moved and seconded and approved by the commission. Staff confirmed the building is in use and recommended acceptance pending the two remaining items.
Background details: Staff told the commission the city solicited qualifications for design-build teams in 2023, approved an initial design contract in July 2023 and amended the contract for construction in September 2024. The staff presentation identified specific unforeseen items that increased costs, including electrical service relocation and gas utility relocation requirements.
Next steps: Staff will complete the remaining delivery/installation and punch-list tasks; the city will host a ribbon cutting on the date announced.