Oakland Park plans staged move to new Sky Building; Collins library to be renovated, temporary relocation planned
Summary
City staff described a multi-month plan to move municipal operations from City Hall to the Sky Building and relocate library services temporarily to the Jocko Building while Collins Building renovations proceed for the Horizon development on City Hall property.
Get email alerts on the Facilities And Development topic
No spam. Unsubscribe anytime.
City staff provided a multi-step timeline on Aug. 6 for an extensive municipal move related to the Horizon downtown development, including staged relocations of city departments, a temporary library site and a schedule to have the new Sky Building ready in time for fall commission meetings.
The plan: staff said initial tenant build-out and IT/network work for the Sky Building are under way and that the commission chambers and audiovisual systems will be dismantled and reinstalled in phases so the commission can meet in the new chambers by the October meeting. The city will vacate current City Hall and the municipal building to make way for the Horizon developer’s work; staff said some temporary power disconnections and demolition (the Omega Church demolition has already occurred) will precede construction.
Library plan and timing: Collins Building renovation will continue; the library will temporarily relocate to the Jocko Building while Collins is finished (expected early 2026). Staff said that Collins will be modernized but that the city is still assessing whether an expanded Collins or an alternate permanent site is optimal for long-term library services; decisions will follow further review of costs and usage.
Why it matters: The municipal move and Horizon demolition/construction will affect parking, permitting and access downtown for months. Staff noted the county’s large air- and seaport projects and the city’s need to preserve parking capacity, which influenced the decision to prioritize public parking access at the Sky Building.
Timing and milestones: staff gave an overview: September — permitting steps and FPL disconnection work; October — staged vacating of facilities and Sky Building commissioning for commission meetings; November–December — property closings with the Horizon developer and construction start; 2026 — visible construction activity (Greenleaf Park first) and continued Collins renovation work.
Commission remarks: Commissioners asked for specifics about the library’s services while at the Jocko Building and about parking impacts for downtown businesses; staff said the temporary site would be smaller and not house all current meeting-room amenities, and committed to working with businesses (for example, Funky Buddha) on parking contingencies during the transition.
What’s next: staff will return with specific schedules for department moves, library program continuity planning and public-notice plans about temporary disruptions to parking and services.