Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Public Works Streets topic
No spam. Unsubscribe anytime.
Council approves $110,071 change order for 2025 street preservation; total contract rises to $716,612
Summary
Lewiston City Council authorized a $110,071.12 change order to the 2025 Street Preservation (seal and fog coat) contract with Herco Inc., increasing the contract to $716,612.33 after crews encountered thicker pavement and poor subgrade requiring additional work.
Get email alerts on the Public Works Streets topic
No spam. Unsubscribe anytime.
The Lewiston City Council on July 28 approved Change Order No. 2 to the 2025 Street Preservation (seal and fog coat) contract with Herco Inc., adding $110,071.12 and raising the total contract amount to $716,612.33.
Public Works Director Dustin Johnson told councilors the additional cost arose after crews exposed pavement that was about twice as thick as expected and found subgrade areas that required more removal and reconstruction than the quantities included in the original bid. Johnson said the city typically estimates thickness before bidding, but actual field conditions sometimes require a full reconstruction rather than preservation treatments. The city had budgeted for these projects and is using preservation funds that also support reconstruction on Fifth Street.
Councilor Schroeder moved and the motion was seconded to approve the change order and authorize the mayor to sign. Councilor Forsman asked about the remaining balance in the street preservation fund and how the remainder will be used; Director Johnson said funds are sufficient and that the city planned to use the program funds for Fifth Street reconstruction, which is expected to start soon.
Ending: The change order passed on council vote. Director Johnson and staff will proceed with the additional work under the revised contract with Herco Inc.

