Wausau Board of Public Works approves vendor authorizations, contractor pay estimates and a completion-date extension for downtown project
Summary
At its Aug. 19 meeting the Wausau Board of Public Works authorized two asphalt vendors for city purchases, approved contractor pay estimates for pavement marking and mall redevelopment work, extended a downtown redevelopment completion date for Pembroke Companies to Oct. 31, and moved into closed session to consider contractor prequalification.
Get email alerts on the Public Works Contracts topic
No spam. Unsubscribe anytime.
The Wausau Board of Public Works on Aug. 19 approved authorizations for two asphalt suppliers, accepted multiple contractor pay estimates for ongoing public-works projects, and extended the completion date for the Downtown Mall redevelopment after hearing that another contractor's schedule had caused delays.
City Attorney Anne Jacobson and Alan Wasilowski, sitting in for Eric Lindman, presided over a meeting in which Department of Public Works staff said one bid for a 2025 slip-line repair project came in higher than the department's estimate and that staff would consult with the sewer division and return the matter to a future meeting.
The board voted to allow the Department of Public Works to purchase asphalt materials from both American Asphalt and RC Pavers so crews can secure material when needed. DPW staff said the city has used both local vendors for years and that relying on a single supplier could impede operations during peak paving periods. A motion to authorize purchases from both vendors passed.
The board also approved a two-month extension to Pembroke Companies' contract completion date for the 2025 Downtown Mall redevelopment. DPW staff said Stevens Construction's schedule for building work on the site has delayed Pembroke's ability to finish by the contract date of Sept. 1; the board approved changing the completion date to Oct. 31, 2025, "without any penalty, liquidated damages, or anything of the sort," as moved by a board member and seconded by another board member.
Separately, the board approved pay estimate No. 1 for the 2025 pavement-marking project, a pay request of $110,877.23 reviewed by the sign shop, and pay estimate No. 5 for the 2025 Mall Redevelopment Phase 2 in the amount of $477,459.14, which staff said had been reviewed and approved by Garrett Lisonbee, project engineer with CORE. Both motions were moved, seconded and approved.
The board approved a Portland cement concrete license application for Hamlin Construction Company after a staff review and voted to enter a closed session under Wisconsin Statute 19.85(d) to deliberate on contractor prequalification statements for the 2025 asphalt milling project and the 2025 athletic parking lots project.
On the slip-line repair project, staff reported a single bid from Pembroke Companies at $462,882, which exceeded the department's estimate; no award or formal action was taken at the meeting and staff said they will confer with the sewer department and return with a recommendation.
Board members occasionally deferred items to allow additional review. A proposed GHD change order was not acted on; members said several were not sufficiently familiar with the document and asked that it be brought back for further review.
Votes at a glance - Motion: Approve minutes from the Aug. 12 meeting. Outcome: Approved (motion moved and seconded; vote recorded as "Aye"). - Motion: Authorize DPW to procure asphalt materials from American Asphalt and RC Pavers. Outcome: Approved. - Motion: Extend Pembroke Companies' Downtown Mall redevelopment completion date from Sept. 1, 2025, to Oct. 31, 2025, without liquidated damages. Outcome: Approved. - Motion: Approve pay estimate No. 1 for the 2025 pavement-marking project, $110,877.23. Outcome: Approved. - Motion: Approve pay estimate No. 5 for 2025 Mall Redevelopment Phase 2, $477,459.14. Outcome: Approved. - Motion: Approve Portland cement concrete license for Hamlin Construction Company. Outcome: Approved. - Motion: Convene closed session pursuant to Wisconsin Statute 19.85(d) to deliberate on prequalification statements for the 2025 asphalt milling project and the 2025 athletic parking lots project. Outcome: Approved.
The board did not award the slip-line repair contract after staff reported a single bid above estimate; the bid amount disclosed was $462,882 from Pembroke Companies and staff indicated they will return with a recommendation after consulting the sewer department. A GHD change order was also deferred for further review.
The board's actions will affect several city projects, including downtown streetscape and parking work. Staff flagged scheduling dependencies with private contractors as the reason for the Downtown Mall extension; funding sources and broader financial impacts were not specified during the meeting.
The Board of Public Works will revisit the slip-line repair bid and the GHD change order at future meetings, according to staff comments at the Aug. 19 session.