Commission defers Ocala Road PUD after traffic and intergovernmental concerns

5760682 · August 11, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The planning commission deferred a planned-unit development for 3 commercial buildings near Interstate 840 and Ocala Road (REZ-25014), citing need for more comprehensive traffic planning, interlocal coordination with Smyrna and pending third-party traffic review.

The Rutherford County planning commission on Aug. 11 deferred consideration of REZ-25014, the Ocala PUD proposed by Laws Bolden and SEC representatives, after staff and commissioners urged a broader, coordinated traffic and utility approach for the Interstate 840/Ocala Road corridor.

The applicant asked to rezone roughly 21 acres north of Interstate 840 for a three-building commercial development with approximately 155,000 square feet of space shown on the concept materials. Planning staff said the site sits inside the county’s Amaville Road Employment Center land-use area and that adjoining development activity — including large housing projects annexed by the town of Smyrna — is accelerating demand and complicating traffic and sewer planning.

Mike (county staff) summarized a recent TDOT coordination meeting that identified several needed improvements: a traffic signal at the intersection of Amaville Road and Ocala Road, a signal on the eastbound 840 ramp and turn-lane improvements at the westbound ramp. Staff and TDOT noted the cumulative effect of multiple projects and said a comprehensive, multi-project approach would better determine required off-site improvements and cost-sharing arrangements.

Applicant representative Rob Molchan and Laws Bolden said the plan was intended to provide flexible, locally oriented “flex-space” for smaller businesses and that the project team had narrowed access to two Ocala Road entrances and preserved a 95-foot landscape buffer. “We’re happy to contribute toward a light — happy to pay our fair share,” Bolden told the commission, but both he and the applicant urged a practical path forward to avoid indefinite delay.

Commissioners, staff and the applicant discussed cost-sharing for major traffic improvements. County attorneys and staff said Rutherford County currently lacks a formal fee-in-lieu or roadway cost-sharing mechanism for unincorporated development comparable to some municipalities; establishing an interlocal or cost-share framework with the town of Smyrna and other developers will take time. Staff also said third-party traffic review of the applicant’s study was pending.

After discussion, the commission voted to defer REZ-25014 to give staff and the applicant time to coordinate traffic solutions, interlocal arrangements and complete third-party review. Several commissioners emphasized the need to develop a consistent, repeatable cost-share and nexus method for corridor improvements to avoid ad hoc or piecemeal fixes.

Next steps: the applicant and staff will continue TDOT coordination, complete the county’s third-party traffic review, and explore cost-share options with Smyrna and other developers. The application will return to the commission after staff has gathered the additional analyses and interlocal recommendation.