Summary
District staff presented early unaudited fiscal-year 2024–25 results showing a roughly $305,000 operating surplus on a $156 million budget, $5.3 million remaining in the capital projects fund and a general fund balance the district reported as $48.35 million (unaudited).
Get email alerts on the Unaudited Financials topic
No spam. Unsubscribe anytime.
Finance staff presented preliminary, unaudited results for fiscal 2024–25 and outlined major fund movements and remaining capital project balances.
Mark Adams, a district staff member, and district staff described three major lines: the capital projects fund, capital reserve and the general fund. Adams said the district began the year with about $19 million in the capital projects fund and spent roughly $13.6 million to date, leaving about $5.3 million to complete ongoing renovation and roofing projects.
Adams said the capital reserve started the year around $15 million; unaudited results show a net decrease of about $795,000 (a figure Adams noted is net of approximately $800,000 in interest income on investments), leaving the capital reserve near its prior level for the fiscal year. On the general fund, Adams said the district expected a roughly $305,000 surplus on a $156 million budget; he characterized the overall unassigned fund balance as essentially flat at about $12.9 million after routine adjustments and board actions.
Adams said the district’s total reported fund balance as of the preliminary results was roughly $48.35 million (unaudited). He cautioned the figures are preliminary and subject to change as auditors review balances and as the district completes remaining payrolls, accruals and inter-district billing; staff said the formal audited statements will be available after the external audit concludes.
Why it matters: The preliminary surplus and remaining capital project funds affect planned renovations and the district’s reserve strategy; staff said they will return with more detailed audited numbers at the September finance meeting.