Board awards $4.26 million HVAC contract for Jerry Whitehead Elementary
Summary
Trustees approved a $4,257,616 contract with Raymond Brothers Construction Inc. to replace cooling systems at Jerry Whitehead Elementary School; district staff said the work addresses remaining "pod"‑type schools and that heating and cooling are separate systems.
Get email alerts on the Capital‑projects topic
No spam. Unsubscribe anytime.
The Washoe County School District Board of Trustees voted 7‑0 on July 29 to award bid 25‑111‑BD‑05‑DA for mechanical upgrades at Jerry Whitehead Elementary School to Raymond Brothers Construction Incorporated for $4,257,616.
Tammy Zimmerman, the district’s chief facilities officer, told trustees the contract is for replacement of the school’s cooling systems; the school’s heating and cooling are separate systems. "This is our last pod type school for that, but it is solely for the purposes of cooling," Zimmerman said. She added the district had begun investigating an icing issue related to condensate or roof drains and was coordinating maintenance and safety work prior to winter.
Trustees asked whether longer‑term alternatives, such as geothermal systems, had been considered. Zimmerman said ground‑source heat pumps exist at some new district schools but replacing Jerry Whitehead’s system with a one‑off solution would create maintenance and training challenges for district staff; the district prefers consistent systems across schools.
Trustee Westlake made the motion to award the contract and Clerk Woodley seconded. The board approved the contract 7‑0 and Zimmerman said staff will continue work to address the icing concern before winter.
Contract details - Bid: 25‑111‑BD‑05‑DA - Contractor: Raymond Brothers Construction Incorporated - Amount: $4,257,616 - Scope: Cooling system replacement at Jerry Whitehead Elementary (final "pod" school in planned upgrades)
Votes at a glance - Motion: "Award the bid 25‑111‑BD‑05‑DA to Raymond Brothers Construction Incorporated for mechanical upgrades at Jerry Whitehead Elementary School in the amount of $4,257,616." Mover: Trustee Westlake; Second: Clerk Woodley. Tally: Yes 7, No 0. Outcome: approved.