City council approves Lehi Ranch subdivision and 20-year development agreement for Village 1 project
Summary
After a public hearing, the Lincoln City Council certified an addendum to the Village 1 EIR and approved tentative subdivision maps and a 20-year development agreement for the Lehi (Veil) Ranch project on roughly 241 acres in Village 1.
Get email alerts on the Development:veil Ranch topic
No spam. Unsubscribe anytime.
The Lincoln City Council on July 22 approved a set of entitlements for the Lehi (also referenced as Veil) Ranch project, a proposed 241-acre residential subdivision within the Village 1 Specific Plan area, and introduced a 20-year development agreement by title.
City staff presented the project as a phased residential subdivision that would create a mix of low- and medium-density housing, roughly 1,237 units overall across Village 1 allocations included in the approved specific plan footprint, with about 40 acres of open space and roughly 9 acres of parks tied into a multi-mile trail network that will connect with nearby neighborhoods.
City planners told the council the proposal is covered by the city's existing 2012 Village 1 Specific Plan environmental impact report (EIR) and that staff had prepared an addendum concluding the Lehi Ranch project would not introduce new or more severe environmental impacts beyond those analyzed in the Village 1 EIR. Adrienne Graham, the project's environmental consultant, told the council the EIR and its cumulative analysis already accounted for other regional projects and growth when it evaluated traffic and other impacts.
Developer representatives said they expect the work to be phased over several years and highlighted public amenities including multiple trails and park sites. Tony Frasier of Frasier Design Group, representing the applicant, said the project is intended to provide housing that supports downtown and other commercial areas and that infrastructure improvements tied to the subdivision (including a 30-inch water line segment) are part of the early phases.
Council discussion ranged from questions about cumulative traffic impacts on nearby county roads to water infrastructure and timing. Staff and the project team said traffic impacts were evaluated in the Village 1 EIR and that some intersections will remain affected at build-out; the specific plan includes mitigation and an infrastructure financing program. On water, staff said each phase will require hydraulic modeling and that developers are required to design, size and pay for needed water improvements; city engineers said the city is updating a water master plan and will review project-specific modeling during design.
On votes, council approved an addendum finding under CEQA, approved the large-lot and small-lot tentative subdivision maps and waived first reading to introduce the 20-year development agreement by title only. Council statements recorded in the meeting show a mix of support and at least one council "no" vote during the roll calls. The council also heard public testimony from nearby residents who asked about water-line routing and timing of infrastructure work and from residents concerned about weeds and fire hazards on adjacent unbuilt parcels.