Council approves $674,640 change order for Dry Fork Greenway; water main relocation drives cost

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The council approved Change Order No. 3 to the Mega KC Corporation contract for the Dry Fork Greenway project, adding $674,640.20 to the contract (new total $4,279,341.12). The largest single item is a $644,784.45 water-main relocation; funding combines water-fund contribution, project reserves and a $155,000 capital improvements allocation.

The Excelsior Springs City Council on July 21 approved Change Order No. 3 to the contract with Mega KC Corporation for the Dry Fork Greenway project, increasing the contract by $674,640.20 to a new total of $4,279,341.12.

Chad Birdsong, Public Works director, told the council the change order contains five line items: sloped paving at a reinforced concrete box for $4,905.14; a reinforced sidewalk tow wall for $10,101.30; replacement of an existing sanitary sewer encasement for $13,312.57; curb-and-gutter elevation adjustments for $1,536.74; and a water-main relocation for $644,784.45. Birdsong said the total of those items is $674,640.20.

Funding for the change order was described in detail. Birdsong said the water fund will contribute $380,000 toward the water-main relocation because the Caldwell portion is outside the original project limits. Project reserves would provide $139,640.20, and the Capital Improvements Committee allocated $155,000 earlier the same day to cover the remainder. Birdsong said the net effect leaves roughly $20,000 available for additional change orders.

Birdsong said the project team expects the Missouri DNR permit “at any time,” and that the water-main work was estimated to take about 60 days. He clarified the 60-day estimate referred to the water-main segment rather than full project completion; above-ground work and remaining tasks would continue after the water-main is complete. He and other council members discussed the routing of the water main through Caldwell Street; Birdsong said the work will require a narrow concrete trench patch (roughly a 4-foot strip) and that a full street restoration or overlay could follow in a later resurfacing program.

The council approved Resolution No. 15-92 on roll call; all members present voted yes.