Board approves sidewalk and paving change orders, and on-call engineering for Northside waterline
Summary
The board approved change orders for paving packages A and B, adding sidewalk and milling work, and authorized an on-call professional-services agreement with Arcadis for the Northside waterline replacement (NTE $50,000).
Get email alerts on the Public Works Projects topic
No spam. Unsubscribe anytime.
The Goshen Board of Public Works and Safety approved several engineering items affecting street paving, sidewalks and waterline construction.
For asphalt paving package B (Plymouth Avenue and related work), the board approved change order No. 1 to add sidewalk replacements through driveways and alleys to meet ADA cross-slope requirements. The change order adds $66,800, increasing the contract roughly 1.4% to $4,633,727.
The board also approved change order No. 3 to asphalt paving package A to add additional asphalt milling on Keystone Drive and Eisenhower Drive and to rebuild a traffic signal loop at Weymouth tied to Kercher Road work. That change order adds $30,122 and brings the contract to $2,269,706.70.
Separately, the board approved a professional services on-call agreement with Arcadis for construction-phase engineering assistance on the Northside waterline replacement project, with a not-to-exceed allowance of $50,000. Staff said retaining the original design firm allows for faster response to unforeseen field conditions during construction.
Each motion carried unanimously.