Board hears capital-project progress; district says phase work largely complete and $4.2 million under budget pending bids
Summary
District architects and the construction manager told the Eastport-South Manor board that phase 1 of the capital project is nearly complete, phase 2 work is underway, and the combined program shows a $4.2 million favorable variance before October bid results.
Eastport-South Manor Central School District trustees heard a monthly capital-project update Sept. 17 from H2M (the district architects) and Park East Construction (the construction manager) on the district's multi-phase renovations and additions.
Project presenters said three of the four buildings in phase 1 (Dayton, South Street and Eastport elementary schools) are closed out, the junior/senior high work is nearly complete, and phase 2—an addition and multiple alterations at the high school plus elementary renovations—remains active. The presenters reported work-progress items including gym-floor refinishes, window and door installations, HVAC and unit-ventilator replacements, new teachers' desks and cubbies in UPK classrooms, masonry repointing and underpinning and shoring for the new high-school…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat