Summary
The Oklahoma City Water Utilities Trust approved a master sales agreement with Badger Meter to keep buying automated meters for an ongoing replacement program that began in February 2023; staff said the project will replace about 30,000 meters per year and the agreement runs through fiscal year 2032.
Get email alerts on the Metering Amr Ami topic
No spam. Unsubscribe anytime.
The Oklahoma City Water Utilities Trust on Aug. 12 approved a master sales agreement with Badger Meter to continue purchases of automated meters for the utility’s multi-year meter-replacement program.
General Manager Ron Browning told trustees the utility selected Badger Meter in February 2023 to upgrade from direct-read to automatic meter-reading equipment and that the program is replacing about 30,000 meters per year. “This agreement will enable us to continue buying the meters from Badger,” Browning said, and he told the trust the contract will run through fiscal year ’32.
The program began with a pilot year, Browning said, and the utility’s own crew is carrying out the replacements. Trustees sought no additional information and a motion to approve the master sales agreement passed.
Trust staff and Browning characterized the vote as an approval of the master purchase agreement only; no additional project budget changes or financing measures were proposed during the discussion. Browning said the multi-year plan remains on schedule to complete within about eight years from its 2023 start.
No mover or second was named in the transcript and no roll-call tally was recorded in the public record excerpt provided. The action was recorded as approved in the meeting minutes.