Summary

The HRA voted to contribute up to $75,000 from economic development funds toward construction of a year-round restroom at a City of Akeley park, contingent on final bids; the board approved the motion by voice vote.

Hubbard County HRA approved a motion to contribute up to $75,000 from budgeted economic-development (EDA) funds to help the City of Akeley complete construction of a year-round restroom serving a local park.

What the board approved

The board voted, by voice, to provide up to $75,000 toward the restroom project. Mary (staff member) said Akeley's initial bid estimates were "just north of $200,000," though staff expected the city to obtain final bids and to reduce the county contribution to the difference once the exact cost is known.

Funding sources and local context

Mary noted the HRA had EDA dollars available this year that could cover the request. The Parks Department previously contributed $65,000 to related parking improvements, and Mary said the community had recently received an additional $20,000 from a local bank, reducing the remaining shortfall.

Mary also supplied data from Placer AI showing increased visitors tied to the parking lot and suggested the restroom would support local businesses and trail users. The board discussed soliciting additional community donations and potential participation by the Minnesota DNR but approved the contribution to move the project forward.

Vote and next steps

A board member moved to approve "up to $75,000"; another board member seconded. The motion carried by voice vote. Staff said the county contribution will be reduced if actual bids come in lower than the estimate and that the city would submit final bids for the board to administratively allocate the funds.

Ending

Staff will track final bids and adjust the county's contribution to the lesser amount needed to complete the restroom; no additional appropriations were made at the meeting beyond the authorized up-to amount.