Daviess County to resurface KY 298, finish KY 662 as KYTC funds allocated; Baird Road drainage contract increased
Summary
County officials accepted Kentucky Transportation Cabinet rural secondary program recommendations to resurface Kentucky 298 and finish Highway 662, and approved a supplemental agreement adding $36,000 to a Baird Road drainage project, bringing that contract to $116,000.
Get email alerts on the Roads And Infrastructure topic
No spam. Unsubscribe anytime.
Daviess County Fiscal Court accepted Kentucky Transportation Cabinet (KYTC) rural secondary program recommendations on Aug. 7, approving resurfacing and base repairs on local routes and a supplemental contract increase for a drainage structure on Baird Road.
At a meeting where KYTC representative Scott Phelps outlined the county’s award from the program, Phelps said total statewide funding was $1,300,000.02 and Daviess County would receive 25 percent — the maximum — or $447,787, with the county’s portion at $872,846. Phelps recommended resurfacing Kentucky 298 (with base repairs where failure was identified) and finishing Highway 662 to the Hancock County line, and using any remaining funds for base repairs and culvert replacements on other rural secondary roads.
The court later approved the rural secondary program as recommended by KYTC, excluding flex funds. County engineer Dirk (last name not specified in the record) told the court he had reviewed Phelps’ list and agreed with the recommendations. The court’s approval was adopted by voice vote.
Separately, the court approved supplemental agreement Change No. 1 for a drainage-structure construction on Baird Road (CR 1240). The project originally approved in a prior session was not to exceed $80,000; bid results and project adjustments prompted an added $36,000, bringing the new agreement total to $116,000. The county’s funding share remains at 20 percent under the rural secondary bridge project program; the supplemental increase follows bid number 252605. The court approved the supplemental agreement by voice vote.
Phelps said work on roads with documented base failures is included in the project scope; additional base failures not in the initial proposal would be handled with remaining funds before contractor pay-out. He said the timing of contractor work depends on the KYTC process in Frankfort after the court’s approval of meeting minutes.
The court did not specify implementation dates for resurfacing work. No public opposition or alternative project lists were recorded during the discussion.
Votes at meeting: the court approved (by voice) the rural secondary program as recommended (excluding flex funds) and approved the supplemental agreement change No. 1 for the Baird Road drainage project.