Urbandale Community School District approves $84,131 in HVAC change orders for Webster work
Summary
The Urbandale Community School District board approved two change orders totaling $84,131 for unexpected HVAC hardware repairs at Webster during a special meeting; a third related proposal of about $35,000 will be considered Aug. 11.
The Urbandale Community School District board on a 4-0 vote approved two change orders totaling $84,131 to address unexpected HVAC hardware issues discovered while work is under way at Webster Elementary.
District staff told the board the work discovered during system disassembly includes seized dampers, actuators and valves that must be replaced or repaired to avoid additional downtime and higher costs later. “What these change orders are relating to is the actual hardware. So dampers and actuators and valves and things of that nature on the actual equipment that as we go…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat