Staff seeks $10,000 contingency increase for College Estates Park restroom contract

5615014 · August 21, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Public Works staff asked the Oxnard City Council to approve a $10,000 increase to the contingency for a restroom replacement contract with At Your Service Construction and Energy, citing unforeseen sewer damage and a pending electrical relocation required by Southern California Edison.

Taylor Gambino, civil engineer for Public Works, told the Oxnard City Council staff is recommending a $10,000 increase to the contingency for the College Estates Park restroom replacement contract with At Your Service Construction and Energy.

Gambino said the additional contingency would raise the contract's not-to-exceed value to $429,980. "It is our recommendation that city council approve and authorize an additional contingency amount of $10,000 with At Your Service Construction and Energy for a new not to exceed contract value of $429,980 for the restroom improvement project located at College Estates Park," Gambino said.

The contract was originally awarded on Feb. 4, 2025, with a base value of $381,800 and a 10% contingency of $38,180, which produced a prior not-to-exceed total of $419,980, Gambino said. He described two change orders that have increased the cost pressure on the contingency: Contract Change Order 1, a $29,750 replacement of a collapsed sewer line discovered during demolition; and a pending Contract Change Order 2, a $14,500 relocation of electrical service required by Southern California Edison.

Gambino said the sewer line deterioration was not visible until the restroom foundation was removed and that the relocation of the power pedestal is shown in project photos. He described the additional contingency as intended to cover the presently needed change order and "any future minor requirements to complete the project." The project will use a prefabricated Exilu restroom to replace the previous unusable restroom and utility room.

Staff reported there are sufficient appropriations in the project budget. Gambino said the public restroom improvement project (C2305) is funded with approximately $1.5 million from the General Fund and $1,000,000 in Measure O funds, for a total allocation of about $2.5 million in fiscal year 2024-25. "There's sufficient budget appropriations to fund this change order increase," he added.

No formal council action or vote is recorded in the provided transcript excerpt; Gambino concluded by asking if there were any questions.