Sparks approves design, construction management contract for water-reclamation facility boiler replacement

5561692 · August 12, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The City Council unanimously approved a contract with Carollo Engineers for design and construction management services to replace near-term boilers at the Truckee Meadows Water Reclamation Facility, with Sparks’ share of the $882,588 agreement at $276,867.86.

The Sparks City Council unanimously approved a contract with Carollo Engineers Inc. on Aug. 11 to complete design and construction management for near-term boiler replacements at the Truckee Meadows Water Reclamation Facility.

The agreement, identified in council materials as AC6135, totals $882,588; the city of Sparks’ share is $276,867.86. Councilmember Abbott moved approval, and Councilmember Rodriguez seconded; the motion carried unanimously.

The city presented the contract after a mechanical failure damaged several pieces of combustion-heating equipment at the plant. Casey Menser, treatment plant manager at the Truckee Meadows Water Reclamation Facility, told the council the failure compromised the facility’s heat loop and led to the loss of three of eight combustion units.

“We were able to have them pivot and be able to focus on fixing that problem,” Menser said of the engineer already under contract. He said Carollo has proceeded to about a 90% design stage and that the city hopes to begin the bid period on Aug. 15, with a return to council on Sept. 8 to consider a construction award.

Menser described steps the design will include to limit future cross-connections and mechanical failures: consolidating multiple disparate heating units, separating boilers and heat exchangers so boilers heat water while exchangers handle process fluids, and planning temporary contingency options such as rental equipment should lead times or other delays occur.

Councilmembers asked about timing and winter readiness. Menser said equipment lead times can be long and the current design work will include contingency plans so the facility can maintain heat if construction is delayed.

Action details

- Motion: Approve agreement AC6135 with Carollo Engineers Inc. for design and construction management services for the Truckee Meadows Water Reclamation Facility heat loop near-term boiler replacement project in the amount of $882,588, Sparks’ share $276,867.86. - Mover: Councilmember Abbott. - Second: Councilmember Rodriguez. - Vote: Motion carries unanimously (yes: 7; no: 0; abstain: 0).

Why it matters

The replacement and redesign respond to an equipment failure that reduced the plant’s heating capacity and aims to consolidate and modernize heating systems to reduce future operational risk. The contract funds design and construction oversight; the council will consider construction bids at a later meeting.