Springville approves MOU to reimburse Buc-ee’s for infrastructure at I‑15 Exit 261
Summary
The Springville City Council approved Resolution 2025-31, authorizing a memorandum of understanding with Buc-ee’s Limited to reimburse the company for certain public improvements needed for a proposed Buc-ee’s travel center at I‑15 Exit 261.
Get email alerts on the Economic Development topic
No spam. Unsubscribe anytime.
Springville City Council approved a memorandum of understanding and Resolution 2025-31 authorizing the city to reimburse Buc-ee’s Limited for public infrastructure improvements tied to a proposed Buc-ee’s travel center near I‑15 Exit 261.
City staff described the MOU as an interim agreement to share costs for arterial streets and utility upsizing needed to serve development at the first exit coming into Springville from the north. "This area off of 261 is not developed at all," said John (staff member), summarizing the city’s responsibilities and the infrastructure items the MOU would cover.
The resolution permits the mayor to execute the MOU "as long as the money is budgeted for and is agreed to by our engineers," John said during the meeting. Under terms discussed at the meeting, the city would reimburse Buc-ee’s $625,000 toward curb-to-curb work on arterial streets (described in the presentation as 1,400 North and 2,600 West) and would pay upsizing costs for sewer and water lines that exceed what Buc-ee’s needs. The city also agreed to reimburse Buc-ee’s 100% for a water-line bore to run beneath I‑15.
Stan Beard, director of development real estate for Buc-ee’s, addressed the council and described the company’s operations and expectations for the site. "This is, as we all know, it's our first store in Utah, and it belongs here," Beard said, adding that typical Buc-ee’s locations create substantial customer draw and employment. He said Buc-ee’s expects to hire "200 plus jobs, full time" with a starting wage he stated as $18.20 an hour.
Beard and staff repeatedly cautioned that the MOU is an interim step and that final cost numbers remain under engineering review. John said the parties (the city, UDOT and Buc-ee’s) had not yet finalized all cost figures and that numbers would be put on paper before final reimbursement amounts were executed.
Council members moved and seconded the resolution and took a roll-call vote. Council members recorded in the roll call as voting yes were Mike, Craig, Jake, Logan and Mindy. The motion carried.
Why it matters: The MOU commits the city to partial reimbursement for major street and utility improvements linked to private development at a freeway exit. Those public investments and any final reimbursement amounts will affect the city budget and the timetable for construction on the site.
What’s next: City staff said engineering and budget details remain to be finalized; the resolution authorizes the mayor to sign the MOU provided funds are budgeted and engineering review supports the figures.