Collierville awards $1.37 million resurfacing contract for three road segments
Summary
The board approved a construction contract with Standard Construction Company for resurfacing roughly 8 lane miles across three Collierville road segments; project reimbursed 80% through a TDOT/MPO program.
Get email alerts on the Public Works Roads topic
No spam. Unsubscribe anytime.
The Collierville Board of Mayor and Aldermen approved a construction contract with Standard Construction Company for the Town's Resurfacing of Various Streets Phase 2 project.
Deputy Town Engineer Tim Gualtney told the board the project covers three segments: Houston Levee (Winchester to south of the railroad), Progress Road (Keogh Road to Shelby Drive) and Shelton Road (Yorktown to Carver/Arlington), including minor widening near 348 Shelton and the MLGW substation frontage. The scope includes mill and overlay of about eight lane miles, localized base repairs, curb, gutter and sidewalk replacement, ADA upgrades and new striping and signage.
The procurement team received two qualified bids; Standard Construction provided the low responsive bid at $1,373,097.91. The contract is a unit-price agreement with 270 calendar days to complete work. Gualtney said the project was submitted for funding through the Memphis Metropolitan Planning Organization and the town entered a TDOT local programs contract in September 2020; the town will be reimbursed 80% of eligible expenditures.
Aldermen asked whether resurfacing on Houston Levee would reach the railroad crossing; staff said work would stop shy of the tracks and railroad crossings and that crossings and ties are typically the railroad's responsibility to tie into town pavement. The board approved the contract unanimously.
Votes: Motion to award construction contract to Standard Construction Company — Ayes: Hall, Jordan, Marshall, Stamps, Robbins, Mayor Frazier.
Why it matters: The project repairs and upgrades roughly eight lane miles of arterial and neighborhood streets, includes ADA work and sidewalk repairs, and is largely funded through a regional transportation program.
What remains: Staff will hold a preconstruction meeting with the contractor to finalize sequencing; town officials said Shelton Road may be an early work area due to curb/gutter scope; the contractor has 270 days to complete the work.