District outlines high-school remodel phasing; primary-school and stadium bids recommended to board
Summary
District staff reviewed phasing and updated turnover dates for the Westonka High School remodel, and presented low bids for two primary-school projects and a stadium project; staff recommended approval of primary-school alternates and most stadium scopes but deferred roofing and track-surfacing awards pending further vetting.
District staff and project consultants gave a detailed construction update at the October regular board meeting, describing phased turnover dates for new science rooms, administration space and athletic facilities and presenting bid results for multiple projects.
For the high-school remodel, staff said phase 1 science areas on the lower level had a target turnover in mid-November, with main-level furniture delivery scheduled for Nov. 26. Additional lower-level areas were slated to open after Thanksgiving, with the full academic wing intended to be ready around winter break; administration and counseling areas…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat