Council approves AIA amendment for Fire Station No. 2; members pressed contractor on change orders, wetlands and schedule
Summary
The council approved an amendment to the AIA agreement for Fire Station No. 2. Contractor representatives said change orders must be approved by the owner and targeted construction duration is about 12 months; commissioners raised questions about wetlands setbacks, retaining-wall design and long-term building durability.
Zion — The Zion City Council on Oct. 7 approved an amendment to the AIA agreement for the planned Fire Station No. 2 and heard design and construction questions from council members and staff.
Why it matters: the amendment moves the project closer to contractor selection and a guaranteed maximum price (GMP). Council members sought clarity about who approves change orders, site constraints tied to wetlands and a retaining wall, and the project schedule.
John Camosse, president…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat