Summary

The commission accepted Chesapeake Utilities of Maryland’s final reconciliation report and authorized a one-time credit for legacy Elkton customers after staff verified the calculations; commissioners voted unanimously to authorize the refund.

The Public Service Commission voted to accept Chesapeake Utilities of Maryland Inc.’s 2025 strategic infrastructure development and enhancement (STRIDE) final reconciliation report and to authorize the company to refund an overcollection amount as a one‑time credit to the affected accounts.

Staff findings: Mark Riley of commission staff said Chesapeake filed a 2025 STRIDE reconciliation report and later refiled a corrected report. Staff confirmed refund calculations in the company’s table 1 were accurate and that the legacy class structure used for calculating refunds was the one in effect when the STRIDE costs were collected. Riley said customers who began service after the date of the final order will not receive a refund because the surcharge applied only to legacy Elkton customers. The STRIDE surcharge had been in effect only for Elkton legacy customers; staff said the company is proposing to refund the overcollection by applying a one‑time credit using rates in table 1.

Company representation: Bridal Quinn (company counsel) appeared in support of staff’s comments and confirmed the company is ready to implement the refund.

Commission questions: Commissioner Linton asked whether refunds would go to customers of all three consolidated companies; staff and counsel clarified the refund applies to legacy Elkton customers only.

Commission action: The commission moved to accept the company’s final reconciliation factor report and authorized a one‑time credit using rates in table 1. Commissioners McLean, Linton, Sussman and Barbet voted aye.

Ending: Staff said the calculations were confirmed; the commission authorized Chesapeake Utilities to proceed with the refund to legacy Elkton customers.