Frangill Road improvements: two work zones open and drainage work ongoing; schedule extended to Sept. 2026
Summary
Design and construction consultants reported that Work Zones 1 and 2 on Frangill Road are open to the public, crews are active in Work Zone 3 with a revised traffic‑management plan, and the overall project schedule now runs to September 2026 after time extensions for utilities and weather.
Get email alerts on the Transportation Infrastructure topic
No spam. Unsubscribe anytime.
Consultants and the town’s construction‑inspection team updated the council on the Frangill Road improvement project on June 18, reporting progress across multiple work zones, community outreach and a revised schedule that extends the project into fall 2026.
Kimley‑Horn’s representative said Work Zone 1 (from Southwest 180th Street to Sterling Drive) is complete and open and that Work Zone 2 recently opened to traffic. Contractors continue construction in Work Zone 3 (Tiffany Drive to Caribbean Boulevard) and distributed a revised maintenance‑of‑traffic (MOT) pattern to affected residences.
Public‑information staff said door‑to‑door outreach has focused on the lateral streets impacted by the next phase. The town’s consultant reported three official rain days credited to the contractor because wet weather suspended work; a time extension was granted to accommodate unanticipated underground utility conflicts and inclement weather. Current project duration as reported is July 2024 to September 2026.
Why it matters: the Frangill Road project includes multimodal and drainage upgrades that affect residents’ daily access and will require continued construction phasing and neighborhood outreach as crews complete later zones.
Ending: Council members were told monthly progress meetings will continue and that staff will provide updates as the schedule evolves.