Legacy Park soil remediation ahead of schedule; Stantec reports 63% of soil export complete
Summary
Stantec project manager Emma Jones told the council the Legacy Park and municipal complex site is ahead on soil export and about 46% complete on soil import, with site prep expected to finish by year‑end and the design phase continuing toward a GMP estimate for construction.
Emma Jones, owner’s representative from Stantec, updated the council on the Legacy Park and Municipal Complex remediation and site‑preparation work on June 18, reporting quantified progress numbers and a year‑end target for the remediation phase.
Jones said the project had exported about 62,392 tons of soil (approximately 2,836 truckloads),…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat