Legacy Park soil remediation ahead of schedule; Stantec reports 63% of soil export complete

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Stantec project manager Emma Jones told the council the Legacy Park and municipal complex site is ahead on soil export and about 46% complete on soil import, with site prep expected to finish by year‑end and the design phase continuing toward a GMP estimate for construction.

Emma Jones, owner’s representative from Stantec, updated the council on the Legacy Park and Municipal Complex remediation and site‑preparation work on June 18, reporting quantified progress numbers and a year‑end target for the remediation phase.

Jones said the project had exported about 62,392 tons of soil (approximately 2,836 truckloads), representing roughly 63% of the export work, and imported about 89,286 tons (about 4,095 truckloads), which she estimated at about 46% complete. “We are about 63% complete with the export of the soils...soil import is 89,286 tons...approximately 46% complete,” Jones told the council.

Why it matters: the remediation and soil movement are the site’s critical path items; the project team said progress on export/import will determine the schedule for the next phase of capital construction and the GMP estimate that the council will review in a future meeting.

Jones said typical weather delays had occurred but overall the team considers the remediation ahead of schedule; she listed completion of soil remediation and site prep as targeted for the end of the year or the start of next year and said the design work is ongoing, with a phase‑2 estimate (GMP) to follow design completion.

Ending: Stantec said it would return with a phase‑2 estimate and GMP once design finishes; council members thanked the consultant for the update and had no additional questions at the meeting.