Sponseller Design Group presented revisions to the Brickworks Lot 1 plan at a Planning Commission workshop, asking for several setback and encroachment modifications and reporting improved connectivity while planning staff and residents pressed for a direct connection to Wissner Avenue and fuller forest-conservation accounting.
Get email alerts on the Brickworks Lot1 topic
No spam. Unsubscribe anytime.
Sponseller Design Group representatives presented revisions to the Brickworks Lot 1 preliminary site and forest conservation plans at a Planning Commission workshop on July 21, arguing their changes improve connectivity, increase on‑site open space and bring the design closer to the city’s expectations. Commissioners and nearby residents pressed the applicant on several requested modifications, forest-conservation accounting and whether the road network provides adequate pedestrian connections.
Applicant summary: Robert Sponseller and Jennifer Chen said revisions focus on four categories: open-space and forest-conservation siting, improved site circulation and connectivity, additional architectural detail, and four requested dimensional modifications. They said the plan now exceeds the minimum on-site open-space requirement (1.04 acres) and is close to meeting the forest‑conservation minimum (0.85 acres) after adding roughly 10,000 square feet (about 0.22 acres) of forest conservation area on the southeast corner of Lot 1 and additional street trees where feasible. The applicant said their revised connectivity ratio improved to 1.75 from about 1.3 by realigning streets and adding a future stub toward Wissner Avenue; the target in staff guidance is 1.8.
Modifications requested (applicant) - Rear-yard reduction: reduce the rear-yard requirement from 20 feet to as little as 7 feet in places to avoid creating alleys wider than neighborhood streets; sponsor said this still yields ~44 feet between building faces across alleys in most places and leaves larger open-space areas elsewhere. - Rear-yard encroachment/deck depth: allow larger rear decks on alley-facing units (up to roughly 5 feet encroachment on a 7-foot rear yard), requiring relief from the rule limiting projections into the rear yard to half the rear-yard depth. - Side yards at passageways: reduce certain side-yard dimensions from 5 feet to 3 feet at the ends of building groupings to widen pedestrian passageways. - Deck-to-property-line setback: reduce required distances between alley-side decks and the property line from 5 feet to as little as 1 foot 9 inches (proposed 1'9" each side), yielding ~3.5 feet between opposing decks.
Staff and commission concerns Commissioners and staff pressed the applicant to clarify how the reductions would affect livability and service access. Questions focused on parking and servicing: the applicant said parking and garages are interior to units (two-car garages at the lower level) and that alleys provide service access. Commissioner Michelle Lewellen and others asked about trash, curbside access and how residents would enter with groceries; the applicant reiterated that primary vehicle access and garages are from alleys and that front yards face the street. Planning staff cautioned that the proposed 30-foot public right-of-way for the alley (driven by utility locations) is larger than typical townhouse alleys and that the proposed 44-foot building‑to‑building dimension is already wider than many comparable projects.
Connectivity and public comment Staff recommended a public road connection that would ultimately intersect across East/South Street to Wissner Avenue; the applicant said they had provided easements and a future perpendicular stub to support that eventual connection but cautioned a direct 45-degree connector to Wissner would be unsafe. Public commenters from East Frederick Rising (Hannah Nickerson and Vanessa Moreno) urged that the Wisner/Wissner connection be delivered with Lot 1 rather than deferred, saying delayed completion could undermine walkability and transit-oriented development goals.
Forest conservation and open space Applicant and staff agreed to an offline tally of tree counts and credits. The applicant estimated they may avoid or minimize a fee-in-lieu payment after final tree-count reconciliation; staff said the new 10,000-square-foot conservation patch plus street trees would be tallied and the fee in lieu determined during subsequent reviews.
Next steps No formal vote was taken at the workshop. Staff told the commission the revised materials will be resubmitted for formal staff review and a future workshop or hearing; staff identified several outstanding technical items including finalized forest conservation tree counts, architectural package review, and confirmation of traffic and road‑connection engineering.
Ending: The commission and staff asked the applicant to refine the forest conservation tally, provide clearer architectural elevations and to revisit the proposed dimensional reliefs with details on how they affect circulation, service access and open-space delivery.