Council reviews Phase 1 concept and timeline for Main City Park improvements; low bid reported at $1.615 million
Summary
City staff presented the Phase 1 concept, timeline and budget estimate for Main City Park improvements and reported the low construction bid at $1,615,226.
Get email alerts on the Park Improvements topic
No spam. Unsubscribe anytime.
City staff presented a concept plan, timeline and budget estimates for Phase 1 of Main City Park improvements and sought council feedback before returning in August for contract approval.
The presentation reviewed the planning history: concept introduction in February, public-survey input (about 270 responses), committee review, a February 2024 retreat selection of a preferred concept, and approval in July 2024 to proceed to Phase 1 design. Staff said they finalized design through 2024 and the first half of 2025 and that construction documents were prepared before going to bid.
Phase 1 elements described by staff include a new, ADA-accessible gazebo, a new restroom, a sand volleyball pit, new backstops and fencing around the baseball field, upgraded electrical and irrigation infrastructure, increased landscaping and improved walking paths and circulation. Staff said the city would procure the gazebo directly via a state contract to obtain better pricing and that the contractor would install it.
Staff said 10 contractors submitted bids and the low bidder for construction was Visco LLC at $1,615,226. With the gazebo procurement and other line items, staff estimated Phase 1 would cost about $1.715 million. The staff presentation included a specific line item for tree preservation to account for added time and effort needed to protect mature trees during construction. Staff said they expect to return to council in August with a contract award recommendation and intend to complete Phase 1 work before November to support the park's seasonal events and lighting schedule.
Council members asked questions about timeline, tree removal risk and whether particular historic "pioneer" trees would be preserved; staff said the project includes tree-preservation work and that final decisions about removing any tree would come during final design and construction when contractors and arborists evaluate conditions.
No contract award for Phase 1 was approved in the excerpted discussion; staff said they planned to return in August with the contract for council approval.