County engineers outline multi-year bridge work, several replacements and designs advancing
Summary
Engineering staff reported design, survey and construction timelines for several county bridges, with some in-house bridge work expected to finish this fall and other projects slated for 2026–2027 construction.
Get email alerts on the Bridges Engineering topic
No spam. Unsubscribe anytime.
Sullivan County engineering staff updated the committee on progress across a series of bridge projects, including near-term in-house replacements and longer-term designs.
Staff said a draft environmental assessment (EA) for the Bridge 368 project in Pflugertown has been distributed for public comment and posted on the county website; staff expect comments in August and anticipate buying materials for construction next year. Several other projects are in design or field-work stages: Bridge 301 (Cambridge) remains under design with an alternatives report under review and construction planned for 2027; Bridge 51 in Swan Lake and Bridge 283 in Livingston Manor have field work complete and draft design reports starting; Bridge 171 (County Road 75) has a consultant on board and draft designs indicate a potential increase from a 40-foot span to something between 120 and 180 feet, with staff negotiating span and cost trade-offs.
In-house bridge operations are advancing on several fronts: Bridge 270 in Pflugertown (Tiny Bridge 270) is expected to have abutments concrete-placed next week and be complete by September or early October; the Ben Hollow Road replacement to eliminate Bridge 277 is progressing; Bridge 400 on County Road 107 is nearly complete following slip-lining of a new pipe into the existing culvert; Cambridge projects include replacement of bridge rail and pier work with estimated completion of several projects in October.
Ending: Engineering staff asked the committee to review designs as they move toward procurement and to note that some projects await utility relocations or additional consultant work before construction can proceed.