Public Works reports paving progress, County Road 94 embankment rebuilt and new traffic signs planned on busy approaches
Summary
Staff reported 20 miles of paving complete so far, chip sealing and contract striping finished under budget, embankment repair on County Road 94 completed using geofabrics and geocells, and new solar-powered flashing signs and speed signs will be installed near troubled intersections.
Sullivan County Department of Public Works staff told the committee that contractor work and in-house crews have advanced paving and road repairs and that traffic-safety equipment will be tested at select locations.
Staff reported about 20 miles of contract paving completed and said roughly 14–15 miles remain to finish the program; in-house crews will handle an estimated additional 120 miles of surface treating and striping work after contractors finish higher-volume roads. Chip sealing and contract…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat