DeSoto lists multi‑million street projects; Daniel Dell and Westmoreland set for construction starts in 2026

5360491 · July 10, 2025

Loading...

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Development Services Director Ahmed Elkes presented the board with design status, cost estimates and target construction dates for 17 capital street projects, including Daniel Dell ($21.1M) and Westmoreland ($20M).

Ahmed Elkes, DeSoto’s development services director, gave the board a capital improvement update that covered 17 projects, including large road reconstructions, intersection improvements, alley repairs and conceptual streetscape work.

Elkes said the Daniel Dell reconstruction will be a four‑lane divided concrete roadway with storm drainage, sidewalks, lighting, landscaping and a new traffic signal at Daniel Dell and Bolton Boone; he estimated the project cost at about $21,100,000 and reported design is about 90% complete with construction expected to start in summer 2026.

He reported Westmoreland reconstruction — another four‑lane divided concrete project with new signals at Westmoreland and Eagle Drive and at Westmoreland and Parkerville — is 100% designed with an estimated $20,000,000 cost and a construction start targeted for January 2026 (bids expected in August). Elkes said Pleasant Run/Broadway whitening is fully designed at an estimated $22,000,000; Hampton Road “character code” streetscape work was described as a multiyear project with $48,000,000 in estimated costs and currently at roughly 50% conceptual design.

Elkes also reviewed a program of alley improvements (eight alleys, approximately $1,000,000 total) that began in May 2025 and reported progress percentages and estimated completion times for those segments.

Board members were given a project map and a note that some projects will move forward only as fund availability allows. No formal votes were taken on capital projects at the meeting.

Ending: Staff said construction schedules and funding updates will return to the board as projects proceed and as bids and funding become available.