Subdivision committee postpones Boonesborough Manor plat and development plan amid Hat Trick Way access, turnaround concerns

5133814 · July 3, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The committee postponed a final record plat and an associated development plan for the Boonesborough Manor / Interstate Park property after extended discussion over whether Hat Trick Way can be accepted as public right-of-way, how Lot 1B would have frontage, and whether the Starbucks parking lot can be relied on for vehicle turnaround.

The Lexington City Subdivision Committee postponed consideration of final record plat FRP 25-14 and development plan MJDP 25-32 for the Boonesborough Manor / Interstate Park property after prolonged discussion about street termination, frontage on an access easement and sewer capacity.

Staff said the amended plat would create 15 lots and dedicate right-of-way for Hat Trick Way, and that applicants had requested a waiver of the subdivision cross-section for Hat Trick Way and a finding that Lot 1B could use an access easement as sole frontage. The staff report listed the usual engineering, traffic, landscape, water-quality and postal sign-offs and added cleanup items (revised plans submitted June 30–July 1) and 17 conditions for the development plan.

Applicant Stephanie Blaine of Palmer Engineering said the project included a new pump station and a holding tank for the stadium area that reduces peak flows into the public system: "we installed a pump station there and basically a holding tank, so that sewage is released at a much lower rate than if it was just coming directly into the public system," she said, adding that Division of Water Quality had reviewed capacity and that the Taco Bell parcel could be served with available capacity today but that future, higher-demand uses could trigger additional sewer improvements.

Much of the committee's discussion centered on Hat Trick Way. The developer proposes to dedicate Hat Trick Way but stop the public street short of a conventional turnaround; instead engineering and the applicant pointed to a paved Starbucks parking lot already on the ground that allows trucks to turn. Staff and committee members repeatedly expressed concern that relying on a private parking lot for turning — and the prospect that a future owner could gate or restrict that lot — would leave the public without a guaranteed turnaround and create long-term maintenance and complaint problems for city staff.

Josh Lewis, representing the owner, said the applicant would pursue an easement over the Starbucks lot if the committee wanted that assurance: "What I would be proposing... would be to have the Starbucks lot have a permanent easement on that lot that says that they can't restrict access from the end of the road moving forward," he said, adding that he expected Starbucks to be conceptually agreeable but that formal approval would be required.

Staff and committee members said the technical committee had reviewed many sign-offs but had not approved the requested waiver(s); staff highlighted that approval of the development plan does not imply approval of the waiver to accept the access easement as public right-of-way. Engineering noted cul-de-sac or hammerhead options are tight because the street is short and detention and topography constrain the site. Committee members asked the applicant to return with clearer options for a permanent and enforceable turnaround or documentation of a permanent easement, and to explore whether a cul-de-sac or an alternate termination could be constructed without harming detention or other site constraints.

After discussion, the committee voted unanimously to postpone action on the final record plat FRP 25-14 and the development plan MJDP 25-32 so the applicant can provide additional details on Hat Trick Way termination (including the possibility of a cul-de-sac or a permanent easement) and follow up on the outstanding waiver questions.

The committee recorded no roll-call vote totals by name; minutes show unanimous support for postponement.

What's next: The applicant was asked to return with clarified language about the timing of sanitary sewer capacity assurances tied to building permits, a proposed permanent easement or other legal instrument to guarantee turnarounds, and any feasible alternative street-termination designs so the planning commission can consider waiver requests with more detail.