Board debates $500,000 reallocation from Colburn capital line; motion fails
Summary
Bonner County Solid Waste requested moving $500,000 from Capital Land Improvements to Capital Other after contractor repairs made asphalt apron replacement unnecessary; commissioners debated holding a reserve for future apron/construction needs and the motion to reallocate failed on roll call.
Get email alerts on the Solid Waste topic
No spam. Unsubscribe anytime.
Solid Waste Director Harrold (presenting) asked the board to reallocate $500,000 from an account originally set aside for capital land improvements (line 2039470) to capital other (2039370) so the department could use the funds for vehicle repairs, a point-of-sale system and other capital needs after the contractor repaired an asphalt apron at the Colburn facility.
Harrold explained the contractor's repairs obviated the immediate need to replace the asphalt apron, and asked to repurpose the budgeted dollars for other capital needs. Commissioners raised concerns that the asphalt in the high-loading area may have a limited life and recommended holding an amount in reserve—Commissioner Doppke suggested $110,000 as an estimate to replace a 10-foot apron area if needed.
Several commissioners asked Solid Waste and county engineering to provide a focused assessment of the Colburn site (anticipated failures, lifespan estimates, and prioritized list of repairs) before releasing large sums for other projects. Director Harrold agreed to return with a more detailed breakdown and prioritized needs.
A motion to approve the reallocation (Resolution No. 2025-540) was made and seconded; after deliberation commissioners voted and the motion failed on roll call.
Ending: The board did not approve the reallocation. Director Harrold will return with a more detailed Colburn capital plan and prioritized list of anticipated repairs, and the $500,000 remains in the original capital land improvements line pending further planning.