Edmond reports timeline, provisional cost estimate for water-treatment expansion

5065409 · June 23, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff said phase 2 of Edmond's water-treatment expansion is underway with completion targeted for February 2027, phase 3 design due end of year and an approximate $192 million figure cited for the next phase pending bids.

Casey Moore, Edmond's director of management services, reported on the city's water-treatment plant expansion during the May 20 strategic-plan workshop.

Moore said phase 2 construction is progressing and is scheduled for completion in February 2027. He said phase 3 design work is expected to finish by the end of this year and be put to bid in early 2026. Moore stated an approximate figure of $192,000,000 for the upcoming phase but cautioned that final costs depend on bid results.

Moore told council staff are monitoring costs and that firm figures will be known once phase 3 is bid. No formal council action was taken during the workshop; staff are to return with updated numbers and schedules as design and procurement progress.