Below are the formal actions taken by the Shawnee County Board of County Commissioners on June 16. All recorded motions passed or were acknowledged by unanimous 3-0 votes unless noted.
- Consent agenda: Motion to approve five consent-agenda items (no individual items detailed in transcript). Outcome: approved 3-0.
- Vouchers: Motion to approve voucher payments totaling $4,115,320.39. Significant listed payments included $617,598.65 to KBS Constructors Inc. (monthly progress payment on state-funded portion of the mental health facility), $78,190 to Choice Solutions LLC (virtual server for the sheriff’s department, paid with federal forfeiture funds), $141,252.18 to Sini and Company (monthly progress payment on courthouse renovation paid from ARPA/SLFRF), and $218,301.54 to King Construction (final payment for bridge replacement). Outcome: approved 3-0.
- Plat: Adopt and approve the combined preliminary/final plat for CRWD No. 2 Tower 1 Subdivision with a 25-foot road-right-of-way dedication. Outcome: approved 3-0.
- Fireworks stand permit: Approve one fireworks-stand application for June 20–July 7, 2025 (site near Topeka Boulevard; applicant had a long history at the location). Outcome: approved 3-0.
- Parks and Recreation contracts/procurements: Approve Kansas Tourism contract (Sunflower Summer Program; state reimbursement up to $20,000), issue RFP for four tennis courts at Casa River Tennis Center (estimated roughly $1.31–$1.4 million with alternates), issue RFQ using CMAR for Gage Park Carousel renovations (Gage Park sales tax funds; $175,000 pledged by Gage Park Improvement Authority for design), and amend Playland site-prep RFP to include additional construction elements funded by Gage Park Improvement Authority funds. Outcomes: all approved 3-0.
- Gage Park Carousel RFQ: Issue RFQ for CMAR delivery for carousel renovation and addition. Outcome: approved 3-0.
- Public Works bridge items: Acknowledge Change Order No. 1 to Contract C460-2024 with King Construction (construction cost decrease $5,561.59); approve Contract C235-2025 with Finney & Turnipseed for design of a culvert replacement at a lump sum cost of $76,400. Outcomes: acknowledged/approved 3-0.
- Court services: Approve Contract C233-2025 with SCRAM Systems for GPS monitoring services for juvenile offenders (36-month term; $2.48 per day per active device; estimated maximum annual $17,198.80). Outcome: approved 3-0.
- Health Department: Approve Contract C231-2025 renewal with Kansas Department of Health and Environment to provide $3,000 for tuberculosis control for period 07/01/2025–06/30/2026. Outcome: approved 3-0.
- Solid Waste: Issue request for quotations for concrete replacement at the County household hazardous waste facility, funded from the 2025 solid-waste operational budget (100% user-fee funded). Outcome: approved 3-0.
- Executive session: Board recessed to executive session on personnel (non-elected personnel discipline matters) and attorney-client privileged consultation regarding third-party management contract and pending litigation for a total of approximately 30 minutes. Board returned with no action taken and adjourned the meeting.
These items reflect the motions recorded on the meeting transcript; where amounts or details were provided in the transcript, they are noted above.