Commissioners approve Great River Energy pole relocation for County Road 2 reconstruction

5672923 · June 24, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved a Great River Energy agreement to relocate an H‑style transmission pole for a County Road 2 reconstruction project; the county expects utility relocation costs on the project to exceed $4 million overall.

The Stearns County Board of Commissioners voted June 24 to approve a transmission pole relocation agreement with Great River Energy needed for a County Road 2 reconstruction project south of Cold Spring.

Public Works Supervisor Jodi Taich told the board the project (SP 70360250) widens the road right-of-way and requires moving at least one Great River Energy H-style transmission pole that would otherwise sit within the roadway shoulder and recovery area near County Road 165. Taich provided the estimate for this individual pole relocation at $242,839.82 and said utility relocation expenses for the overall road project have now risen above $4 million.

Taich noted past agreements with Xcel Energy and Great River Energy and said relocation costs must be paid; the county cannot solicit alternate vendors for utility relocation under the terms with the utilities. Commissioners discussed the costs and Great River Energy’s cooperative structure; one commissioner observed that Great River Energy’s mission is to recover costs for its membership of cooperative utilities.

A motion to approve the relocation agreement was made and seconded; the board approved the motion by voice vote.

Taich also presented the county’s updated five‑year road improvement program later in the meeting (separate action).