County staff reviewed courthouse building improvements, construction and operating costs for a new Law Enforcement Center (LEC), and proposed how costs would be split with the city; discussion focused on estimates, contingencies and staffing implications for new facilities.

County staff reviewed expected 2026 costs for courthouse building improvements and the new Law Enforcement Center (LEC), described a list of anticipated repairs and renovations, and discussed how operating costs and reimbursements with the city would be tracked.

The courthouse budget discussion identified a multi‑phase set of building improvements including painting, sidewalk and asphalt repairs, roof and canopy work, window washing, pipe insulation and retaining wall repairs. Staff estimated a building‑improvement allocation around $140,000 for routine projects, and noted larger courthouse renovation estimates elsewhere in the capital program totaling in the high‑hundreds of thousands for multiple projects (one project line was discussed in the $915,000 range as part of a larger $950,000 total). Staff said some figures in the packet contained a transcription error and clarified the correct numbers during the meeting.

On the Law Enforcement Center, staff presented a separate LEC budget and described assumptions used to calculate operating costs. The county staff said they were budgeting for roughly two‑and‑a‑half positions at the LEC (with staff time split between sites) and used square footage and staffing formulas to estimate utilities, supplies and repairs. Staff and commissioners discussed an approach under which the city would reimburse roughly two‑thirds of certain operating costs and the county would carry one‑third, and they noted that final arrangements would be set in a reimbursement or lease agreement.

Commissioners and staff debated whether to delay some renovation work to build more cash reserves; staff cautioned that delaying construction risks higher costs later. The board asked that staff bring finalized bid information at the July 28 meeting to inform the board’s final budget decision and said that, even if the opt‑out authority is passed, the board could elect not to spend the full amount.

Staff also listed specific capital maintenance items for 2026, including a handrail on the first floor, additional office painting, a water fountain on the third floor, employee furniture replacement, roof access for a satellite building, and asphalt repair at a 4‑H building. Commissioners probed the scope and cost of each item and asked staff to work with maintenance leads on precise estimates.

No formal vote on the courthouse or LEC budgets occurred at the meeting; commissioners asked staff to refine numbers for inclusion in the county’s provisional 2026 budget.