Chase City Elementary demolition to start after teachers move; auction of surplus property set for July 12

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Division staff reported that teachers at Chase City Elementary will move out within weeks, the building turnover to Blair Construction is expected after an auction, and demolition can then commence.

Mecklenburg County Public Schools staff updated the board on the Chase City Elementary School project, saying teachers are scheduled to move out within the next few weeks and an auction has been set for July 12.

Superintendent's staff invited Mr. Dalton to present the Chase City update. Dalton said the teachers are expected to vacate in the coming weeks and that the auction date is set for July 12 at 10 p.m. (as stated in the transcript). After the auction, Dalton said the division expects to turn the building over to Blair Construction, after which demolition can commence.

Board members asked no follow-up questions during the update, and Dalton concluded by thanking the board. The presentation was framed as a project kickoff similar to recent updates on Clarksville Elementary.

The board did not take a separate vote on the construction schedule during the presentation; follow-up implementation steps (site turnover and auction) were referred to facilities staff.