Ada County tables two RFP awards after protests; opens courthouse desk bid from EKC
Summary
Procurement staff told the Ada County Commission that award recommendations for RFP 250278 and RFP 25058 were protested and the board tabled both awards to July 22. The county opened bids for the courthouse information desk (Bid 25063), disclosed one bidder (EKC Incorporated, $144,155) and tabled the award pending administrative review.
Get email alerts on the Procurement topic
No spam. Unsubscribe anytime.
Procurement staff informed the Ada County Commission on July 15 that final ranking and award recommendations on two solicitations were protested and that staff asked the board to retable both awards for further consideration at the July 22 open meeting.
"We were prepared to come to you with no award recommendation today, but we received a protest from Early Alert in response recommendation, to a war letter that was sent to our proposers," procurement staff said regarding RFP 250278 (an incident management–type procurement). The commission voted to table the recommendation to July 22.
Procurement staff then reported a similar situation for RFP 25058 (employee benefits consultant): "We were also prepared to come to you today with the final ranking and award recommendation, but we received a protest from Propel Insurance in response to our recommendation ... Therefore, we'd like to retable this project as well to the 07/22/2025 open business meeting for further consideration." The board tabled that recommendation to July 22.
At the public meeting the county opened bids for Bid 25063 (Ada County Courthouse information desk remodel). Procurement staff said the county received a single bid from EKC Incorporated with a total bid of $144,155, which included the base bid, an additive alternate for three sit/stand electronic stations and a built-in desk, and a $25,000 owner contingency. The commission voted to table award of Bid 25063 to July 22 to allow staff additional time to review administrative requirements.
Why it matters
Protests interrupt the procurement timeline and delay contract awards while staff and the board review submitted challenges. Vendor disputes can affect project schedules and budget planning for county remodeling and consultant services.
Next steps
Procurement staff will meet with the board to discuss the protests and will return recommendations on July 22, 2025. Staff will also review the EKC bid for compliance with procurement rules before recommending an award.